Menu
Log in
<< First  < Prev   1   2   Next >  Last >> 
  • Saturday, January 31, 2004 12:00 PM | James Parnell (Administrator)

    UPDATE - January 2004 It's been fairly quiet since the Summer of 2002 when the City began discharging to Lick Branch under a temporary 2-year agreement to find a final solution - and time is running out. Recently things have heated up again as it now looks pretty obvious that Spencer will not make the August 2004 deadline to stop discharging to Lick Branch and will have to ask the court for their first one year extension (of 2 possible). At a status hearing before Judge Haynes on Friday January 16, 2004 it was explained that the city is awaiting a decision from a federal funding agency (EDA) on a grant to build a pipeline to the Caney Fork River. Meanwhile a citizen opposition group has organized on the river to stop the pipeline and this could jeopardize the funding. This means that Spencer will likely ask for an extension to stay in Lick Branch another year, and may have to look at another alternative - meaning land application might be back on the table.

     For older stories and items on the issue visit peer.org

  • Sunday, October 10, 1999 12:00 PM | James Parnell (Administrator)

    Marta W. Aldrich

    The AP

    COLUMBIA, Tenn. - On a chigger-infested basin along the Duck River, bulldozer-size hydraulic hammers chip away at 26,000 cubic yards of concrete that for 16 years stood as a monument to failure.

    The Tennessee Valley Authority's (TVA) unfinished Columbia Dam will never hold back a drop of water. It is being demolished.

    For hundreds of people who saw their families uprooted and homesteads bulldozed to make way for the project in the 1970s, a bitter taste returned in May with the announcement that the dam would come down.

    "To think that it was all for nothing, it's sad," said Patricia West, 73, whose 156-acre farm was among 12,800 acres acquired. "My heart is still broken."

    The TVA spent about $83 million on the dam between 1969 and 1983, when the project was halted over environmental concerns. The dam's concrete portion was more than 90 percent complete and the project as a whole was nearly half done.

    Except for occasional vandals and rappellers, the site was mostly abandoned until June 1, when demolition crews arrived.

    Rising price tag

    The TVA cited safety among its reasons for the demolition - people fall off dams from time to time - but the price tag also had become prohibitive. Construction and land expenses have risen steeply since 1967, from a projected $50 million then to $200 million.

    Demolition should be finished by January.

    Each weekday from 7 a.m. to 5:30 p.m., hydraulic hammers flake off 15 cubic yards of concrete an hour. The TVA will have spent $2.4 million once the dam is dismantled and broken rock used to reshape the basin to resemble the original site. TVA project manager Dan Ferry said it's an expense of conscience.

    "We're trying to leave this land in as good a shape as we can. We've irritated people enough around here already," he said.

    The TVA, created in 1933 as part of President Franklin D. Roosevelt's New Deal, built a string of power-producing and flood-controlling dams in Tennessee and Kentucky through the 1940s. For the most part, they transformed the character of the flood-prone Tennessee Valley and made large-scale economic growth possible.

    Less well received were TVA tributary dams such as Columbia that came in the 1960s and '70s. Their goals weren't electricity production but local economic development, drinking water and recreation.

    Local business leaders envisioned the Columbia Dam as a precursor to industrial growth for the region. They formed the Upper Duck River Development Association in 1964 and lobbied U.S. Rep. Joe Evins, D-Tenn. He was chairman of the powerful House subcommittee on public works and a friend of Columbia banker and dam proponent Lon MacFarland.

    Evins secured the first funding in 1969 for a two-dam project on the Duck River that would begin with Normandy Dam and finish with the more expensive Columbia Dam 100 miles to the north.

    "He just thought it would be a great benefit to that area," said Robert Moore Jr., who worked for the late congressman in the early 1960s.

    Attorney Frank Fly, who represented environmental groups and farmers opposing the project, saw it as pork-barrel politics at its worst.

    "The few who were going to get money at Columbia were in favor of this project. Everyone else was against it," he said.

    Fly believes the TVA was dragged unwillingly into the job. The agency conducted three feasibility studies - in 1933, 1951 and 1966 - that recommended against building the dam. However, the last study was revised and presented a more favorable case, showing $1.20 of benefits for every $1 of cost and setting the stage for federal funding.

    The TVA quickly began acquiring the flat, rocky land on the outskirts of Columbia, 40 miles south of Nashville, where farms and homes dotted rural communities.

    Few residents able to fight

    Few residents had the resources or know-how to fight the giant federal utility when TVA officials ordered them to sell or face condemnation.

    "They'd say, `If you don't like what we give you, you can hire a lawyer,"' said Buddy Derryberry, whose parents' country store was bought in the land rush.

    "After that, the elderly folks were never the same. It destroyed them. I remember seeing 80-year-old people just sit down and cry like a baby because they didn't want to leave home."

    Environmentalists pounced on the Columbia project, which would impound the Duck River on relatively level land. They said the dam would turn the tributary into a murky, algae-filled lake.

    They mailed small bottles of smelly green water to Tennessee's congressional delegation, took the matter to federal court and managed to get several construction delays, angering local supporters who saw the environmentalists - mainly out-of-state groups - as meddlers.

    But the courts and later government regulators eventually sided with the TVA and allowed the project to proceed.

    The momentum shifted by 1977 when the U.S. Fish and Wildlife Service added a number of freshwater mussels to its list of endangered species, including two in the Duck River: the birdwing pearly mussel and the Cumberland monkeyface pearly mussel. Efforts to transplant the inch-long creatures to other streams were unsuccessful.

    "That pretty well sunk us there," Ferry said of the Columbia project.

    Business leaders disappointed

    In Columbia, seat of the fifth-fastest-growing county in Tennessee and home to the Saturn car plant, business leaders remain disappointed.

    "The dam represented our future," said ex-City Manager William Gentner. "Without a good water supply, we're at the whim of Mother Nature. And I have yet to see a city grow without ample water."

    Columbia resident Ralph Meece is more direct.

    "There will be a time when Columbia will be thirsty and stinky," said Meece, who joined two dozen protesters outside the demolition site in June. "At this rate, human beings will be the endangered species."

    Chamber of Commerce President Tony Beyer said most locals backed the dam in the early years but support eroded.

    "I think people just got tired of hearing about it," Beyer said. "The only enthusiasm lately has been over what to do with the land now that they're tearing down the dam. Everybody has their own idea."

    The TVA has recommended transferring all 12,800 acres to the Tennessee Wildlife Resources Agency to manage. Some land would be for public use, including sites for two schools, a fire hall, a civil-defense training center and recycling station. Part would be reserved for another potential water-supply project. And a fraction would go for residential use.

    In the meantime, former landowners and their heirs are suing the TVA in federal court to reclaim their land.

    Patricia West is among the 125 people listed in the complaint. She wants back the farm where she and her husband raised three children and tended cattle, tobacco and hay for 23 years.

    "No one will ever know the strain and hardship this put on us," said West, whose husband died of a heart attack six years after the move.

    "I've cussed and cried. . . . If I could get that land back, I'd die happy."

    Copyright (c) 1999 Seattle Times Company, All Rights Reserved.

    http://community.seattletimes.nwsource.com/archive/?date=19991010&slug=2988099 

  • Tuesday, May 11, 1999 12:00 PM | James Parnell (Administrator)

    Duck-River Opportunities Project (DROP) started in 1999 to monitor-&-improve the water quality of the Duck River and its tributaries. Drop was funded by the Duck River Protection Endowment which was created following a court settlement between Dana Corporation and the EPA.  

    TSRA initially created DROP after John McFadden spoke to TSRA's board of directors in 1999, asking the organization to sponsor his plan to use the fund to improve water quality in the Duck-River watershed.  DROP was to be a collaborative effort between the protection fund, TSRA, and project director John McFadden.  Marshall Spencer acted as TSRA chair for the project. 

    With John McFadden, an independent consultant, heading up the project, DROP used the protection fund for its projects.  After those funds were depleted, DROP obtained grants from TWRA and other grantors.  Under Marshall Spencer’s supervision, TSRA processed the invoices for materials used in all of the site-specific conservation projects in DROP and kept records of grant funds spent for reporting purposes. 

    Following a verbal agreement with Leslie Colley of The Nature Conservancy, DROP agreed to limit its focus to "the Lower Duck-River watershed", which for that agreement was below Columbia dam. 


    DROP Successes:

    • A large part of DROP's efforts were in the Spring Hill area, since fast-paced suburban expansion was heavily impacting Duck-River tributaries in that area.  DROP mobilized many residents and area volunteers to help with weekend projects. Many of the volunteers used for tree planting and for riverbank stabilization were TSRA members, but eventually the residents took the lead in those projects.
       
    • John McFadden and Marshall Spencer kept an eye on TDOT projects in the watershed and even advised them on how to use best practices to minimize water pollution during construction.  The biggest TDOT project monitored was the first phase of the 4-lane expansion of U.S. highway 412 / TN 99 east of Hohenwald in Lewis County.  That project is now in its third phase.
       
    • It was through DROP's persistence that fraudulent record-keeping in Mt. Pleasant's sewage-treatment department was discovered.  High levels of sewage-related pollutants in Grassy Branch belied what the department's records stated. That eventually led to two federal convictions of department employees. 


<< First  < Prev   1   2   Next >  Last >> 
Powered by Wild Apricot Membership Software